TSM Weekly Report

Week: 2026-09-14 - 2026-09-20  ·  Faten Rusli
Generated at 2026-09-20 21:33 UTC

KPI (MTD) · September 2026

EMPLOYEE MPS
54
Team avg: 69.7
65.953.654JulAugSep
T1 Quality of sourcing
0%
Total RFPs: 20
Result_count: 5
Result, %: 25%
Weight: 0
23.69.60JulAugSep
Show tenders (5)
  • 4435RFP L04 - AUTONIC17.9%diff: 15.6%
  • 4384RFP L04 - Camera Desk Mount17.9%diff: 9.2%
  • 4371Event Organizer Dermies Max 10th Anniversary Gala Event17.9%diff: 15.9%
  • 4346Glassware - FPS 367317.9%diff: 0%
  • 4284Maintenance Panel Utama Tegangan Menengah17.9%diff: 62.1%
T2 Timing of sourcing
10%
Total RFPs: 20
Result_count: 20
Result, %: 100%
Weight: 10
9.51010JulAugSep
Show tenders (20)
  • 4450Souvenir Package for event17.9%diff: 32.6%
  • 3770[TAHAP 2] PENGIRIMAN UNIT TIPE DOZER 2X818F A BLADE KE MUKUT BARITO UTARA17.9%diff: 10.1%
  • 4295RFP.L07 PIPA BESI17.9%diff: -17.9%
  • 4435RFP L04 - AUTONIC17.9%diff: 15.6%
  • 4408AC DAIKIN SPLIT STANDAR R32 THAILAND FTC 50XV1417.9%diff: -17.9%
  • 4384RFP L04 - Camera Desk Mount17.9%diff: 9.2%
  • 4371Event Organizer Dermies Max 10th Anniversary Gala Event17.9%diff: 15.9%
  • 4346Glassware - FPS 367317.9%diff: 0%
  • 3849RFP. L07 PISTON PUMP ( Finalisasi )17.9%diff: -2.5%
  • 4305RFP. L07 SENSOR DAPPRA NPN SAFETY17.9%diff: -6.7%
  • 3766[FINALISASI HARGA] PENGIRIMAN UNIT TIPE WHEEL LOADER 636D KE KERANG DAYO KALTIM17.9%diff: -6.6%
  • 4137[PERPANJANG WAKTU] Kebutuhan Fuel Pump Injection (FIP) Seri BH6P120 PN S00016266+0117.9%diff: -20.8%
  • 4284Maintenance Panel Utama Tegangan Menengah17.9%diff: 62.1%
  • 4251Paket Souvenir - Semarang17.9%diff: -11.1%
  • 4226(COSTING CALCULATION) PENGIRIMAN UNIT TIPE GRADER 915F SC KE RIAU17.9%diff: -17.9%
  • 4203Digital Walkie Talkie BAOFENG DM-X 5W17.9%diff: -0.6%
  • 4197(COSTING CALCULATION) PENGIRIMAN UNIT TIPE LOADE 636D KE SAMARINDA KALIMANTAN TIMUR17.9%diff: -17.9%
  • 4175Pembuatan Ruang Kerja OLX (Lampung)17.9%diff: -17.9%
  • 4119(COSTING CALCULATION) PENGIRIMAN UNIT TIPE DOZER 822D KE KONAWE SULAWESI TENGGARA17.9%diff: 20.3%
  • 3757Pengadaan & Pergantian Instalasi HVAC OT1 & OT3 RS di Palembang17.9%diff: -17.9%
T3 Zero-bid RFPs
10%
Total RFPs: 20
Result_count: 20
Result, %: 100%
Weight: 10
9.51010JulAugSep
Show tenders (20)
  • 4450Souvenir Package for event17.9%diff: 32.6%
  • 3770[TAHAP 2] PENGIRIMAN UNIT TIPE DOZER 2X818F A BLADE KE MUKUT BARITO UTARA17.9%diff: 10.1%
  • 4295RFP.L07 PIPA BESI17.9%diff: -17.9%
  • 4435RFP L04 - AUTONIC17.9%diff: 15.6%
  • 4408AC DAIKIN SPLIT STANDAR R32 THAILAND FTC 50XV1417.9%diff: -17.9%
  • 4384RFP L04 - Camera Desk Mount17.9%diff: 9.2%
  • 4371Event Organizer Dermies Max 10th Anniversary Gala Event17.9%diff: 15.9%
  • 4346Glassware - FPS 367317.9%diff: 0%
  • 3849RFP. L07 PISTON PUMP ( Finalisasi )17.9%diff: -2.5%
  • 4305RFP. L07 SENSOR DAPPRA NPN SAFETY17.9%diff: -6.7%
  • 3766[FINALISASI HARGA] PENGIRIMAN UNIT TIPE WHEEL LOADER 636D KE KERANG DAYO KALTIM17.9%diff: -6.6%
  • 4137[PERPANJANG WAKTU] Kebutuhan Fuel Pump Injection (FIP) Seri BH6P120 PN S00016266+0117.9%diff: -20.8%
  • 4284Maintenance Panel Utama Tegangan Menengah17.9%diff: 62.1%
  • 4251Paket Souvenir - Semarang17.9%diff: -11.1%
  • 4226(COSTING CALCULATION) PENGIRIMAN UNIT TIPE GRADER 915F SC KE RIAU17.9%diff: -17.9%
  • 4203Digital Walkie Talkie BAOFENG DM-X 5W17.9%diff: -0.6%
  • 4197(COSTING CALCULATION) PENGIRIMAN UNIT TIPE LOADE 636D KE SAMARINDA KALIMANTAN TIMUR17.9%diff: -17.9%
  • 4175Pembuatan Ruang Kerja OLX (Lampung)17.9%diff: -17.9%
  • 4119(COSTING CALCULATION) PENGIRIMAN UNIT TIPE DOZER 822D KE KONAWE SULAWESI TENGGARA17.9%diff: 20.3%
  • 3757Pengadaan & Pergantian Instalasi HVAC OT1 & OT3 RS di Palembang17.9%diff: -17.9%
T4 RFPs with 3+ bids
34%
Total RFPs: 20
Result_count: 17
Result, %: 85%
Weight: 40
23.22434JulAugSep
Show tenders (17)
  • 4450Souvenir Package for event17.9%diff: 32.6%
  • 3770[TAHAP 2] PENGIRIMAN UNIT TIPE DOZER 2X818F A BLADE KE MUKUT BARITO UTARA17.9%diff: 10.1%
  • 4295RFP.L07 PIPA BESI17.9%diff: -17.9%
  • 4435RFP L04 - AUTONIC17.9%diff: 15.6%
  • 4408AC DAIKIN SPLIT STANDAR R32 THAILAND FTC 50XV1417.9%diff: -17.9%
  • 4384RFP L04 - Camera Desk Mount17.9%diff: 9.2%
  • 4346Glassware - FPS 367317.9%diff: 0%
  • 3849RFP. L07 PISTON PUMP ( Finalisasi )17.9%diff: -2.5%
  • 4305RFP. L07 SENSOR DAPPRA NPN SAFETY17.9%diff: -6.7%
  • 4137[PERPANJANG WAKTU] Kebutuhan Fuel Pump Injection (FIP) Seri BH6P120 PN S00016266+0117.9%diff: -20.8%
  • 4284Maintenance Panel Utama Tegangan Menengah17.9%diff: 62.1%
  • 4251Paket Souvenir - Semarang17.9%diff: -11.1%
  • 4203Digital Walkie Talkie BAOFENG DM-X 5W17.9%diff: -0.6%
  • 4197(COSTING CALCULATION) PENGIRIMAN UNIT TIPE LOADE 636D KE SAMARINDA KALIMANTAN TIMUR17.9%diff: -17.9%
  • 4175Pembuatan Ruang Kerja OLX (Lampung)17.9%diff: -17.9%
  • 4119(COSTING CALCULATION) PENGIRIMAN UNIT TIPE DOZER 822D KE KONAWE SULAWESI TENGGARA17.9%diff: 20.3%
  • 3757Pengadaan & Pergantian Instalasi HVAC OT1 & OT3 RS di Palembang17.9%diff: -17.9%

Operational Metrics

Workflow

Active RFP
25
6 companies
Team avg: 25
+6 (+32%) vs prev
910192508-2408-3109-0709-14
Show details (25)
  • 3699Renovasi Kitchen Rumah Sakit di Palembang - 1st Submission0 bids
  • 3770[TAHAP 2] PENGIRIMAN UNIT TIPE DOZER 2X818F A BLADE KE MUKUT BARITO UTARA3 bids
  • 3893[Preliminary Stage] CMEP Astro facilities 2026 Jabodetabek0 bids
  • 4137[PERPANJANG WAKTU] Kebutuhan Fuel Pump Injection (FIP) Seri BH6P120 PN S00016266+013 bids
  • 4160RFQ Kontrak Jasa Perbaikan Rolling door0 bids
  • 4295RFP.L07 PIPA BESI7 bids
  • 4305RFP. L07 SENSOR DAPPRA NPN SAFETY6 bids
  • 4346Glassware - FPS 36733 bids
  • 4360RFQ Kontrak Jasa Maintenance Genset0 bids
  • 4371Event Organizer Dermies Max 10th Anniversary Gala Event1 bids
  • 4382RFP L04 - STAINLESS 3041 bids
  • 4384RFP L04 - Camera Desk Mount3 bids
  • 4406RFQ BEDLINER HILUX0 bids
  • 4408AC DAIKIN SPLIT STANDAR R32 THAILAND FTC 50XV143 bids
  • 4435RFP L04 - AUTONIC6 bids
  • 4447RFQ SPECATALOG EXAVATOR 220D4 bids
  • 4450Souvenir Package for event6 bids
  • 4490RFP L09 - Sourcing Kebutuhan Seragam Karyawati/Staff Perempuan (blazer dan rok)4 bids
  • 4550Pengadaan Lampu Philips 45 pcs5 bids
  • 4572(COSTING CALCULATION) PENGIRIMAN UNIT TIPE WHEEL LOADER 655D KE GORONTALO3 bids
  • 4585RFQ Kebutuhan Lampu Philips Downlight Pomeron 7W 4000K - FPS 38335 bids
  • 4588RFP L19 - INVERTER GD20-0R4G-S2 MERK INVT4 bids
  • 4593RFQ Perpanjang Izin K3 Pontianak - FPS 37802 bids
  • 4606Selenoid Valve - FPS 37942 bids
  • 461110333876 - RFQ Tensimeter Digital OMRON1 bids
New RFP
12
Public — 12, Private — 0
Team avg: 10.2
+2 (+20%) vs prev
35101208-2408-3109-0709-14
Show details (12)
  • 4382RFP L04 - STAINLESS 3041 bids
  • 4435RFP L04 - AUTONIC6 bids
  • 4447RFQ SPECATALOG EXAVATOR 220D4 bids
  • 4450Souvenir Package for event6 bids
  • 4490RFP L09 - Sourcing Kebutuhan Seragam Karyawati/Staff Perempuan (blazer dan rok)4 bids
  • 4550Pengadaan Lampu Philips 45 pcs5 bids
  • 4572(COSTING CALCULATION) PENGIRIMAN UNIT TIPE WHEEL LOADER 655D KE GORONTALO3 bids
  • 4585RFQ Kebutuhan Lampu Philips Downlight Pomeron 7W 4000K - FPS 38335 bids
  • 4588RFP L19 - INVERTER GD20-0R4G-S2 MERK INVT4 bids
  • 4593RFQ Perpanjang Izin K3 Pontianak - FPS 37802 bids
  • 4606Selenoid Valve - FPS 37942 bids
  • 461110333876 - RFQ Tensimeter Digital OMRON1 bids
New stage
3
2 companies
Team avg: 5.6
-2 (-40%) vs prev
005308-2408-3109-0709-14
Show details (3)
  • 3770[TAHAP 2] PENGIRIMAN UNIT TIPE DOZER 2X818F A BLADE KE MUKUT BARITO UTARA3 bids
  • 4295RFP.L07 PIPA BESI7 bids
  • 4447RFQ SPECATALOG EXAVATOR 220D4 bids
Completed RFP
8
Public — 8, Private — 0
Team avg: 11
+3 (+60%) vs prev
305808-2408-3109-0709-14
Show details (8)
  • 3770[TAHAP 2] PENGIRIMAN UNIT TIPE DOZER 2X818F A BLADE KE MUKUT BARITO UTARA3 bids
  • 3786RFQ konsultan perencanaan1 bids
  • 3849RFP. L07 PISTON PUMP ( Finalisasi )3 bids
  • 4126RFQ IT Asset5 bids
  • 4197(COSTING CALCULATION) PENGIRIMAN UNIT TIPE LOADE 636D KE SAMARINDA KALIMANTAN TIMUR4 bids
  • 4251Paket Souvenir - Semarang8 bids
  • 4371Event Organizer Dermies Max 10th Anniversary Gala Event1 bids
  • 4435RFP L04 - AUTONIC6 bids
Public Completed <3 bids
2
1 companies
Team avg: 4.2
+1 (+100%) vs prev
001208-2408-3109-0709-14
Show details (2)
  • 3786RFQ konsultan perencanaan1 bids
  • 4371Event Organizer Dermies Max 10th Anniversary Gala Event1 bids
Public Completed without winner
2
1 companies
Team avg: 7.6
+1 (+100%) vs prev
101208-2408-3109-0709-14
Show details (2)
  • 3786RFQ konsultan perencanaan1 bids
  • 4371Event Organizer Dermies Max 10th Anniversary Gala Event1 bids

Execution

Workbench cards (delivery, relevance, Relevant → Bids) are calculated on first-phase tenders only — TSM scores the full invited pool in phase 1; phases 2+ are shown for reference and excluded from these cards.
Workbench tasks delivery rate
97.4%
722 done / 741 total
Team avg: 65.9%
+1.0 (+1%) vs prev
97.510096.497.408-2408-3109-0709-14
Show details (15)
  • 3770PENGIRIMAN UNIT TIPE DOZER 818F KE MUKUT BARITO UTARA23 / 23
  • 3786RFQ konsultan perencanaan27 / 27
  • 3849RFP. L07 PISTON PUMP27 / 27
  • 4126RFQ IT Asset40 / 59
  • 4137Kebutuhan Fuel Pump Injection (FIP) Seri BH6P120 PN S00016266+0136 / 36
  • 4197(COSTING CALCULATION) PENGIRIMAN UNIT TIPE LOADE 636D KE SAMARINDA KALIMANTAN TIMUR59 / 59
  • 4251Paket Souvenir - Semarang93 / 93
  • 4295RFP.L07 PIPA HDPE RUCIKA54 / 54
  • 4305RFP. L07 SENSOR DAPPRA NPN SAFETY83 / 83
  • 4346Glassware - FPS 367344 / 44
  • 4371Event Organizer Dermies Max 10th Anniversary Gala Event63 / 63
  • 4384RFP L04 - Camera Desk Mount51 / 51
  • 4408AC DAIKIN SPLIT STANDAR R32 THAILAND FTC 50XV1433 / 33
  • 4435RFP L04 - AUTONIC18 / 18
  • 4450Souvenir Package for event71 / 71
Workbench relevance rate
95.3%
688 relevant / 722 done
Team avg: 72.4%
+11.7 (+14%) vs prev
94.896.283.695.308-2408-3109-0709-14
Show details (30)
  • AI — 215 rel / 260 done
  • 3770PENGIRIMAN UNIT TIPE DOZER 818F KE MUKUT BARITO UTARAT:9 D:9 R:9 (100%)
  • 3786RFQ konsultan perencanaanT:8 D:8 R:8 (100%)
  • 3849RFP. L07 PISTON PUMPT:14 D:14 R:14 (100%)
  • 4126RFQ IT AssetT:19 D:19 R:0 (0%)
  • 4137Kebutuhan Fuel Pump Injection (FIP) Seri BH6P120 PN S00016266+01T:22 D:22 R:11 (50%)
  • 4197(COSTING CALCULATION) PENGIRIMAN UNIT TIPE LOADE 636D KE SAMARINDA KALIMANTAN TIMURT:40 D:40 R:40 (100%)
  • 4251Paket Souvenir - SemarangT:22 D:22 R:22 (100%)
  • 4295RFP.L07 PIPA HDPE RUCIKAT:11 D:11 R:11 (100%)
  • 4305RFP. L07 SENSOR DAPPRA NPN SAFETYT:24 D:24 R:24 (100%)
  • 4346Glassware - FPS 3673T:10 D:10 R:9 (90%)
  • 4371Event Organizer Dermies Max 10th Anniversary Gala EventT:28 D:28 R:28 (100%)
  • 4384RFP L04 - Camera Desk MountT:14 D:14 R:8 (57.1%)
  • 4408AC DAIKIN SPLIT STANDAR R32 THAILAND FTC 50XV14T:13 D:13 R:13 (100%)
  • 4435RFP L04 - AUTONICT:11 D:11 R:10 (90.9%)
  • 4450Souvenir Package for eventT:15 D:15 R:8 (53.3%)
  • TSM — 473 rel / 481 done
  • 3770PENGIRIMAN UNIT TIPE DOZER 818F KE MUKUT BARITO UTARAT:14 D:14 R:14 (100%)
  • 3786RFQ konsultan perencanaanT:19 D:19 R:15 (78.9%)
  • 3849RFP. L07 PISTON PUMPT:13 D:13 R:13 (100%)
  • 4126RFQ IT AssetT:40 D:40 R:40 (100%)
  • 4137Kebutuhan Fuel Pump Injection (FIP) Seri BH6P120 PN S00016266+01T:14 D:14 R:12 (85.7%)
  • 4197(COSTING CALCULATION) PENGIRIMAN UNIT TIPE LOADE 636D KE SAMARINDA KALIMANTAN TIMURT:19 D:19 R:19 (100%)
  • 4251Paket Souvenir - SemarangT:71 D:71 R:71 (100%)
  • 4295RFP.L07 PIPA HDPE RUCIKAT:43 D:43 R:43 (100%)
  • 4305RFP. L07 SENSOR DAPPRA NPN SAFETYT:59 D:59 R:59 (100%)
  • 4346Glassware - FPS 3673T:34 D:34 R:32 (94.1%)
  • 4371Event Organizer Dermies Max 10th Anniversary Gala EventT:35 D:35 R:35 (100%)
  • 4384RFP L04 - Camera Desk MountT:37 D:37 R:37 (100%)
  • 4408AC DAIKIN SPLIT STANDAR R32 THAILAND FTC 50XV14T:20 D:20 R:20 (100%)
  • 4435RFP L04 - AUTONICT:7 D:7 R:7 (100%)
  • 4450Souvenir Package for eventT:56 D:56 R:56 (100%)
Workbench AI: Relevant → Bids
0%
0 applied / 215 denom
Team avg: 1.8%
0 vs prev
000008-2408-3109-0709-14
Show details (14)
  • 3770PENGIRIMAN UNIT TIPE DOZER 818F KE MUKUT BARITO UTARA0 applied / 9 (0%)
  • 3786RFQ konsultan perencanaan0 applied / 8 (0%)
  • 3849RFP. L07 PISTON PUMP0 applied / 14 (0%)
  • 4137Kebutuhan Fuel Pump Injection (FIP) Seri BH6P120 PN S00016266+010 applied / 11 (0%)
  • 4197(COSTING CALCULATION) PENGIRIMAN UNIT TIPE LOADE 636D KE SAMARINDA KALIMANTAN TIMUR0 applied / 40 (0%)
  • 4251Paket Souvenir - Semarang0 applied / 22 (0%)
  • 4295RFP.L07 PIPA HDPE RUCIKA0 applied / 11 (0%)
  • 4305RFP. L07 SENSOR DAPPRA NPN SAFETY0 applied / 24 (0%)
  • 4346Glassware - FPS 36730 applied / 9 (0%)
  • 4371Event Organizer Dermies Max 10th Anniversary Gala Event0 applied / 28 (0%)
  • 4384RFP L04 - Camera Desk Mount0 applied / 8 (0%)
  • 4408AC DAIKIN SPLIT STANDAR R32 THAILAND FTC 50XV140 applied / 13 (0%)
  • 4435RFP L04 - AUTONIC0 applied / 10 (0%)
  • 4450Souvenir Package for event0 applied / 8 (0%)
Workbench TSM: Relevant → Bids
10.4%
49 applied / 473 denom
Team avg: 2.4%
-0.2 (-2%) vs prev
2.76.710.610.408-2408-3109-0709-14
Show details (15)
  • 3770PENGIRIMAN UNIT TIPE DOZER 818F KE MUKUT BARITO UTARA4 applied / 14 (28.6%)
  • 3786RFQ konsultan perencanaan0 applied / 15 (0%)
  • 3849RFP. L07 PISTON PUMP1 applied / 13 (7.7%)
  • 4126RFQ IT Asset7 applied / 40 (17.5%)
  • 4137Kebutuhan Fuel Pump Injection (FIP) Seri BH6P120 PN S00016266+010 applied / 12 (0%)
  • 4197(COSTING CALCULATION) PENGIRIMAN UNIT TIPE LOADE 636D KE SAMARINDA KALIMANTAN TIMUR4 applied / 19 (21.1%)
  • 4251Paket Souvenir - Semarang6 applied / 71 (8.5%)
  • 4295RFP.L07 PIPA HDPE RUCIKA6 applied / 43 (14%)
  • 4305RFP. L07 SENSOR DAPPRA NPN SAFETY6 applied / 59 (10.2%)
  • 4346Glassware - FPS 36732 applied / 32 (6.2%)
  • 4371Event Organizer Dermies Max 10th Anniversary Gala Event2 applied / 35 (5.7%)
  • 4384RFP L04 - Camera Desk Mount2 applied / 37 (5.4%)
  • 4408AC DAIKIN SPLIT STANDAR R32 THAILAND FTC 50XV142 applied / 20 (10%)
  • 4435RFP L04 - AUTONIC2 applied / 7 (28.6%)
  • 4450Souvenir Package for event5 applied / 56 (8.9%)
Avg Bids per RFP (90 d)
4.9
78 RFP (90d)
380 bids total
Team avg: 5.1
-0.3 (-6%) vs prev
5.45.45.24.908-2408-3109-0709-14
Home Winner Rate (90 d)
25%
8 home / 32 with winner (90d)
Team avg: 28.4%
+5.0 (+25%) vs prev
17.918.5202508-2408-3109-0709-14
Show by TSM (1)
  • Faten Rusli — 8 / 32 (25%)
Invited Winner Rate (90 d)
31.2%
TSM: 10 · AI: 1 · Cust: 3
No invite info: 20 / 32 total (90d)
Team avg: 28.4%
-8.8 (-22%) vs prev
42.944.44031.208-2408-3109-0709-14
Show details (32)
  • 2414Karoseri Ambulance Serena Highwaystar?
  • 3104Lampu LED Panel dan Material Kelistrikan?
  • 3109RFQ Riksa Uji K3 - FPS 2397?
  • 3117(Re-open) perpanjangan waktu RFP Pouch canvas custom?
  • 3163RFQ Refill APAR EDC Kombes Sby (FPS 2426)TSM
  • 316410325532 - CONSUMABLE ZONA SOUTH SUMATERACustTSM
  • 3023Produksi Dompet dan Pouch?
  • 3225RFQ Riksa Uji K3 - FPS 2429?
  • 3202RFQ Consumable dan Alat Kerja (Revisi harga)?
  • 3528Mini NotesTSM
  • 3575Trolley Stainless Steel?
  • 2869(Tahap Finalisasi Harga) Renovasi Pengadaan Waterplay - Sekolah di BekasiTSM
  • 2726(Tahap 2 - Perubahan Spek) Fire Rescue Cabinet - Kota BandungAI
  • 3629Kebutuhan Kabel?
  • 348510327013 - SOLAR PERTAMINA DEX (FINALISASI)Cust
  • 3707[NEW SPEC] Tas Spundbond 25x35 - SEMARANG?
  • 3746RFP.L07 AXIAL FAN & DOSING PUMP?
  • 3515RFP.L07 - Pengadaan IT, Camera ( ADR ) Finalisasi harga ( Perpanjangan waktu ke 4 ))TSM?
  • 3903Purifikasi Trafo - 1250 KVA?
  • 3262[TAHAP 3] PENGIRIMAN SOIL COMPACTOR SEM 512 KE SORONG PAPUACust
  • 3834RFQ Relay Octo - FPS 2971TSM
  • 3994RPF. L07 Pengadaan IT ( PT Selamat Sempurna Tbk )TSM
  • 3779FINALISASI NEGO RFQ FPS-ECII-2026-2447 Pembuatan Signage dan Totem Erha Central YogyakartaTSM
  • 4126RFQ IT Asset?
  • 4197(COSTING CALCULATION) PENGIRIMAN UNIT TIPE LOADE 636D KE SAMARINDA KALIMANTAN TIMURTSM
  • 4203Digital Walkie Talkie BAOFENG DM-X 5W?
  • 4251Paket Souvenir - Semarang?
  • 4284Maintenance Panel Utama Tegangan Menengah?
  • 3766[FINALISASI HARGA] PENGIRIMAN UNIT TIPE WHEEL LOADER 636D KE KERANG DAYO KALTIMTSM
  • 3849RFP. L07 PISTON PUMP ( Finalisasi )?
  • 4435RFP L04 - AUTONIC?
  • 3770[TAHAP 2] PENGIRIMAN UNIT TIPE DOZER 2X818F A BLADE KE MUKUT BARITO UTARA?

Summary

Summarising
Total RFP — 190
Summarizing RFP — 41 (21.6% from 190)
Summarizing RFP <3 bids — 8 (19.5% from 41)
Conversion completed→winner
Total RFP — 190
Completed RFP — 134 (70.5% from 190)
Completed RFP with winner — 65 (48.5% from 134)

Team Table last week

TSMActive RFPSummarizing (<3)Completed (<3)Zero bids (summarizing + completed)Workbench delivery %
Faten Rusli2502097.4%

Focus RFP Next Week (Low Liquidity)

RFP IDCompanyRFP nameTSMBidsInvites SSMAcceptance End
4406PT. TRI SWARDANA UTAMARFQ BEDLINER HILUXFaten Rusli0142026-09-21 04:26:20.800000
4382ADR GroupRFP L04 - STAINLESS 304Faten Rusli1662026-09-22 03:00:00
4611PT. TRI SWARDANA UTAMA10333876 - RFQ Tensimeter Digital OMRONFaten Rusli1612026-09-22 08:41:00
4160PT Astro Technologies IndonesiaRFQ Kontrak Jasa Perbaikan Rolling doorFaten Rusli0382026-09-23 05:00:00
4593Arya NobleRFQ Perpanjang Izin K3 Pontianak - FPS 3780Faten Rusli2462026-09-23 05:00:00
4606Arya NobleSelenoid Valve - FPS 3794Faten Rusli2732026-09-24 05:00:00
3699Hospital IndonesiaRenovasi Kitchen Rumah Sakit di Palembang - 1st SubmissionFaten Rusli0182026-09-24 08:00:00
4360PT Astro Technologies IndonesiaRFQ Kontrak Jasa Maintenance GensetFaten Rusli0482026-09-24 17:00:00

Risks & Focus

Weekly snapshot
Active RFP25
Completed8
Avg Bids per RFP4.9
WB Delivery97.4%
WB TSM: Rel → Bids10.4%
Risks
  • Completed RFPs with <3 bids: 2 and growing (2 weeks in a row)
  • Completed RFPs without winner: 2 and growing (2 weeks in a row)
  • Avg Bids per RFP declining (2 weeks in a row)
Focus
  • Increase supplier outreach to improve bid liquidity
  • Follow up on RFPs in summarizing stage — push for winner selection
  • Recruit additional suppliers for RFPs with low bid count